The direct and indirect costs estimated by a contractor for bidding a project is $₹160000$ and $₹20000$ respectively. If the mark up applied is $10\%$ of the bid price, the quoted price (in ₹) of the contractor is

  1. $200000$
  2. $198000$
  3. $196000$
  4. $182000$