0 votes 0 votes The direct and indirect costs estimated by a contractor for bidding a project is $₹160000$ and $₹20000$ respectively. If the mark up applied is $10\%$ of the bid price, the quoted price (in ₹) of the contractor is $200000$ $198000$ $196000$ $182000$ Construction Materials and Management gatecivil-2021-set1 construction-contracts cost-estimation + – Arjun asked Feb 19, 2021 • recategorized Apr 20, 2021 by Chandanachandu Arjun 13.0k points answer See all 0 reply