At a construction site, a contractor plans to make an excavation as shown in the figure.
The water level in the adjacent river is at an elevation of $+20.0$ m. Unit weight of water is $10 \: kn/m^3$. The factor of safety (up to two decimal places) against sand boiling for the proposed excavation is ___________