GATE Civil Engineering
0 votes
A road in a hilly terrain is to be laid at a gradient of $4.5\%$. A horizontal curve of radius $100\:m$ is laid at a location on this road. Gradient needs to be eased due to combination of curved horizontal and vertical profiles of the road. As per IRC, the compensated gradient (in $\%$, round off to one decimal place), is  _______.
in Geomatics Engineering by (2.7k points)
recategorized by

Please log in or register to answer this question.

Answer: