Consider the statements $\text{P}$ and $\text{Q}$.

$\text{P}$: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.

$\text{Q}$: Client's Detailed Estimate is used for controlling costs during the execution of the project.

Which one of the following options is CORRECT?

  1. Both $\text{P}$ and $\text{Q}$ are TRUE
  2. $\mathrm{P}$ is TRUE and $\mathrm{Q}$ is FALSE
  3. Both $\mathrm{P}$ and $\mathrm{Q}$ are FALSE
  4. $\mathrm{P}$ is FALSE and $\mathrm{Q}$ is TRUE