​​​​Consider the statements $\text{P}$ and $\text{Q}$.

$\text{P}$: In a Pure project organization, the project manager maintains complete authority and has maximum control over the project.

$\text{Q}$: A Matrix organization structure facilitates quick response to changes, conflicts, and project needs.

Which one of the following options is CORRECT?

  1. Both $\mathrm{P}$ and $\mathrm{Q}$ are TRUE
  2. $\text{P}$ is TRUE and $\text{Q}$ is FALSE
  3. Both $\text{P}$ and $\text{Q}$ are FALSE
  4. $\mathrm{P}$ is FALSE and $\mathrm{Q}$ is TRUE