A surface water treatment plant operates round the clock with a flow rate of $35 \: m^3/min$. The water temperature is $15^{\circ}C$ and jar testing indicated an alum dosage of $25$ mg/l with flocculation at a $Gt$ value of $4 \times 10^4$  producing optimal results. The alum quantity required for $30$ days (in kg) of operation of the  plant is _______