GATE Civil 2021 Set 1 | Question: 43
A small project has $12$ activities - $\text{N, P, Q, R, S, T, U, V, W, X, Y,}$ and $\text{Z}$ ... $\text{ V }$ (in weeks, in integer) is __________________
A small project has $12$ activities – $\text{N, P, Q, R, S, T, U, V, W, X, Y,}$ and $\text{Z}$. The relationship among these activities and the duration of these activi...