0 votes 0 votes The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O – M – P. The expected completion time (in days) of the project is ________ Construction Materials and Management gate2016-ce-1 numerical-answers structural-engineering construction-materials-and-management project-planning-and-network-analysis + – Milicevic3306 asked Mar 27, 2018 • recategorized May 27, 2021 by Chandanachandu Milicevic3306 11.9k points answer See all 0 reply