Recent questions tagged construction-materials-and-management

0 0 votes
0 0 answers
Which one of the following is utilized to determine the long-term deformation of concrete under sustained loading?CreepShrinkageModulus of ruptureSplit tensile strength
0 0 votes
0 0 answers
In a bituminous mix, the percentage by weight of coarse aggregate, fine aggregate, filler, and bituminous binder is $58,25,12$, and $5$, respectively. The corresponding s...
0 0 votes
1 1 answer
Consider the following statements $(\mathrm{P})$ and $(\mathrm{Q})$ :$(\mathrm{P})$ : Fly ash and ground granulated blast furnace slag can be used as mineral admixtures i...
0 0 votes
0 0 answers
In the context of construction materials, which of the following statements is/are CORRECT?If the characteristic strength is defined as that value below which not more th...
0 0 votes
1 1 answer
Which of the following statements is/are INCORRECT?Bitumen having lower softening point is preferred in warm climate regions.The viscosity of bitumen influences the mixin...
0 0 votes
1 1 answer
The figure shows a network diagram for a construction project. The activities $\mathrm{A}$, $\mathrm{B}$, $\mathrm{C}, \mathrm{D}, \mathrm{E}$, and $\mathrm{F}$ are repre...
0 0 votes
1 1 answer
​​​​Identify the FALSE statement from the following options:The compressive strength of a concrete test specimen can vary depending on its shape and sizeAir-dried and sat...
0 0 votes
1 1 answer
​​​​​​In the context of testing bitumen, which one of the following statements is FALSE:The depth of penetration of needle in the standard penetration test is measured in...
0 0 votes
0 0 answers
If the weights retained on the $2.36 \: \mathrm{~mm}, 1.18 \: \mathrm{~mm}, 600 \: \mu \mathrm{~m}$, and $300 \: \mu \mathrm{~m}$ sieves are $30 \%, 35 \%, 15 \%$, and $2...
0 0 votes
0 0 answers
​​​​In the context of construction project management, which of the following statements is/are true:A dummy activity will consume time and resourcesThe programme evaluat...
0 0 votes
1 1 answer
During determination of the bulk specific gravity of compacted bituminous specimen, the mass in air of the specimen is $1260 \mathrm{g}$ and volume is $525 \mathrm{~cm}^{...
0 0 votes
0 0 answers
​​​​Consider the statements $\text{P}$ and $\text{Q}$.$\text{P}$: In a Pure project organization, the project manager maintains complete authority and has maximum control...
0 0 votes
0 0 answers
​​​​​Consider the following data for a project of $300$ days duration.Budgeted Cost of Work Scheduled (BCWS) = Rs. $200$Budgeted Cost of Work Performed (BCWP) = Rs. $150$...
0 0 votes
0 0 answers
​​​A critical activity in a project is estimated to take $15$ days to complete at a cost of Rs. $30,000$. The activity can be expedited to complete in $12$ days by spendi...
0 0 votes
1 1 answer
​​​​In the context of pavement material characterization, the CORRECT statement(s) is/areThe load penetration curve of $\text{CBR}$ test may need origin correction due to...
0 0 votes
1 1 answer
Consider the statements $\text{P}$ and $\text{Q}$.$\text{P}$: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.$\text...
0 0 votes
1 1 answer
The following figure shows the arrangement of formwork for casting a cantilever $\mathrm{RC}$ beam.The correct sequence of removing the Shores/Props is$\mathrm{S} 1 \righ...
0 0 votes
0 0 answers
The initial cost of an equipment is Rs. $1,00,000$. Its salvage value at the end of accounting life of $5$ years is Rs. $10,000$. The difference in depreciation (in Rs.) ...
0 0 votes
0 0 answers
$\text{M20}$ concrete as per $\mathrm{IS~} 456: 2000$ refers to concrete with a design mix having ____________an average cube strength of $20~ \mathrm{MPa}$an average cyl...
0 0 votes
0 0 answers
Two plates are connected by fillet welds of size $10 \mathrm{~mm}$ and subjected to tension, as shown in the figure. The thickness of each plate is $12 \mathrm{~mm}$. The...
0 0 votes
0 0 answers
Consider the Marshall method of mix design for bituminous mix. With the increase in bitumen content, which of the following statements is/are TRUE?the Stability decreases...
0 0 votes
0 0 answers
In cement concrete mix design, with the increase in water-cement ratio, which one of the following statements is TRUE? Compressive strength decreases but workability incr...
0 0 votes
0 0 answers
Which of the following options match the test reporting conventions with the given material tests in the table?$$\begin{array}{|l|l|}\hline \textbf{Test reporting convent...
0 0 votes
0 0 answers
Match all the possible combinations between Column X (Cement compounds) and Column Y (Cement properties):$$\begin{array} {|l|l|} \hline \textbf{Column X} & \qquad \textbf...
0 0 votes
0 0 answers
To design an optimum municipal solid waste collection route, which of the following is/are $\text{NOT}$ desired:Collection vehicle should not travel twice down the same s...
0 0 votes
0 0 answers
The activities of a project are given in the following table along with their durations and dependency.$$ \begin{array} {|c|c|c|} \hline \textbf{Activities}& \textbf{Dura...
0 0 votes
0 0 answers
It is given that an aggregate mix has $260 \; \text{grams}$ of coarse aggregates and $240 \; \text{grams}$ of fine aggregates. The specific gravities of the coarse and fi...
0 0 votes
0 0 answers
Which of the following equations is correct for the Pozzolanic reaction?$\text{Ca(OH)}_{2}$ + Reactive Superplasticiser + $H_{2}O \rightarrow \text{C-S-H}$$\text{Ca(OH)}_...
0 0 votes
0 0 answers
The project activities are given in the following table along with the duration and dependency.$$\begin{array}{|c|c|} \hline \textbf{Activities} & \textbf{Duration (days...
0 0 votes
0 0 answers
In the context of cross-drainage structures, the correct statement(s) regarding the relative positions of a natural drain (stream/river) and an irrigation canal, is/areIn...
0 0 votes
0 0 answers
In case of bids in Two-Envelop System, the correct option isTechnical bid is opened firstFinancial bid is opened firstBoth (Technical and Financial) bids are opened simul...
0 0 votes
0 0 answers
The activity details for a small project are given in the Table.$$\begin{array}{|cl|cI|cI|}\hline&\textbf{Activity} & \textbf{Duration (days)} & \textbf{Depends on} \\ \h...
0 0 votes
0 0 answers
Contractor $\text{X}$ is developing his bidding strategy against Contractor $\text{Y}$. The ratio of $\text{Y’s}$ bid price to $\text{X’s}$ cost for the $30$ previous bid...
0 0 votes
0 0 answers
As per $IS\:456:2000$, the $pH$ value of water for concrete mix shall NOT be less than$4.5$$5.0$$5.5$$6.0$
0 0 votes
1 1 answer
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following of contract woul...
0 0 votes
0 0 answers
Let the characteristic strength be defined as that value, below which not more than $50 \%$ of the results are expected to fall. Assuming a standard deviation of $4$ MPa,...
0 0 votes
0 0 answers
For a construction project, the mean and standard deviation of the completion time are $200$ days and $6.1$ days, respectively. Assume normal distribution and use the val...
0 0 votes
0 0 answers
Group I gives a list of test methods and test apparatus for evaluating some of the properties of Ordinary Portland Cement (OPC) and concrete. Group II gives the list of t...
0 0 votes
0 0 answers
Consider the following statements:Walls of one brick thick are measured in square metersWalls of one brick thick are measured in cubic metersNo deduction in the brickwork...
0 0 votes
0 0 answers
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of ...