Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following of contract would be most preferred?

  1. EPC contract
  2. percentage rate contract
  3. Item rate contract
  4. Lump sum contract
in Construction Materials and Management edited by
by
4.0k points

1 Answer

0 votes
0 votes
Lumpsum contract d
140 points
Answer: