Recent questions tagged cost-estimation
0
votes
0
answers
1
GATE Civil 2021 Set 2 | Question: 43
An equipment has been purchased at an initial cost of $₹ 160000$ and has an estimated salvage value of $₹ 10000$. The equipment has an estimated life of $5$ years. The difference between the book values (in ₹, $\textit{in integer}$) ... at the end of $4^{\text{th}}$ year using straight line method and sum of years digit method of depreciation is______________
An equipment has been purchased at an initial cost of $₹ 160000$ and has an estimated salvage value of $₹ 10000$. The equipment has an estimated life of $5$ years. Th...
go_editor
5.3k
points
go_editor
asked
Mar 1, 2021
Construction Materials and Management
gatecivil-2021-set2
numerical-answers
cost-estimation
+
–
0
votes
0
answers
2
GATE Civil 2021 Set 1 | Question: 6
The direct and indirect costs estimated by a contractor for bidding a project is $₹160000$ and $₹20000$ respectively. If the mark up applied is $10\%$ of the bid price, the quoted price (in ₹) of the contractor is $200000$ $198000$ $196000$ $182000$
The direct and indirect costs estimated by a contractor for bidding a project is $₹160000$ and $₹20000$ respectively. If the mark up applied is $10\%$ of the bid pric...
Arjun
13.0k
points
Arjun
asked
Feb 19, 2021
Construction Materials and Management
gatecivil-2021-set1
construction-contracts
cost-estimation
+
–
0
votes
1
answer
3
GATE2017 CE-2-3
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following of contract would be most preferred? EPC contract percentage rate contract Item rate contract Lump sum contract
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following of contract woul...
gatecse
4.0k
points
gatecse
asked
Aug 7, 2019
Construction Materials and Management
gate2017-ce-2
construction-materials-and-management
structural-engineering
contracts
cost-estimation
+
–
0
votes
0
answers
4
GATE2019 CE-1: 37
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is ... is targeted for completion in $16$ days, the total cost (in INR) to be incurred by the contractor would be _______
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of ...
Arjun
13.0k
points
Arjun
asked
Feb 14, 2019
Construction Materials and Management
gate2019-ce-1
numerical-answers
construction-materials-and-management
structural-engineering
types-of-construction-projects
cost-estimation
+
–
0
votes
0
answers
5
GATE2016-2-10
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below. ... $11-12$ for the project are, respectively, $25$ and $1$ $1$ nd $1$ $0$ and $0$ $81$ and $0$
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network di...
Milicevic3306
11.9k
points
Milicevic3306
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-2
construction-materials-and-management
structural-engineering
project-planning-and-network-analysis
cost-estimation
+
–
0
votes
0
answers
6
GATE2017 CE-1: 45
The activity details of a project are given below: ... The estimated minimum time (in days) for the completion of the project will be __________
The activity details of a project are given below:$$\begin{array}{|c|c|c|} \hline \text{Activity} & \text{Depends on} & \text{Duration (in days)} \\ \hline P & \dots & 6 ...
Milicevic3306
11.9k
points
Milicevic3306
asked
Mar 26, 2018
Construction Materials and Management
gate2017-ce-1
numerical-answers
construction-materials-and-management
structural-engineering
project-planning
cost-estimation
+
–
To see more, click for the
full list of questions