The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR $5000$ per day.

$\begin{array}{|c|c|c|c|c|} \hline \text{Activity} & \text{Normal Duration (days)}  & \text{Crash Duration (days)} & \text{Normal Cost (INR)} & \text{Crash Cost (INR)} \\ \hline P & 6 & 4 & 15000 & 25000 \\ \hline Q & 5 & 2 & 6000 & 12000 \\ \hline R & 5 & 3 & 8000 & 9500 \\ \hline S & 6 & 3 & 7000 & 10000 \\ \hline T & 3 & 2 & 6000 & 9000 \\ \hline U & 2 & 1 & 4000 & 6000 \\ \hline V & 4 & 2 & 20000 & 28000 \\ \hline \end{array}$

The project is targeted for completion in $16$ days, the total cost (in INR) to be incurred by the contractor would be _______

in Construction Materials and Management edited by
by
11.6k points

Please log in or register to answer this question.

Answer:
Welcome to GATE Civil Q&A, where you can ask questions and receive answers from other members of the community.
Top Users Jun 2023