For a construction project, the mean and standard deviation of the completion time are $200$ days and $6.1$ days, respectively. Assume normal distribution and use the value of standard normal  deviate $z = 1.64$ for the $95 \%$ confidence level. The maximum time required (in days) for the completion of the project would be ________
in Others by (3.9k points)
retagged by

Please log in or register to answer this question.

Answer: