GATE2014-1-40
The flow net constructed for the dam is shown in the figure below. Taking the coefficient of permeability as $3.8 \times 10^{-6}$ m/s, the quantity of flow (in $cm^3/s$) under the dam per meter of dam is __________
The flow net constructed for the dam is shown in the figure below. Taking the coefficient of permeability as $3.8 \times 10^{-6}$ m/s, the quantity of flow (in $cm^3/s$) ...
Milicevic3306
11.9k
points
Milicevic3306
asked
Mar 25, 2018
Irrigation
gate2014-ce-1
numerical-answers
irrigation
dams
water-resource-engineering
coefficient-of-permeability
+
–
0
votes
1
answer
2
GATE2018 CE-1: 39
Variation of water depth $(y)$ in a gradually varied open channel flow is given by the first order differential equation $ \dfrac{dy}{dx} = \dfrac{1-e^{-\frac{10}{3} \ln(y)}}{250 - 45e^{-3\ln(y)}}$ ... in m, up to three decimal places) of flow at a downstream section at $x=1$ m from one calculation step of Single Step Euler Method is ___________
Variation of water depth $(y)$ in a gradually varied open channel flow is given by the first order differential equation$$ \dfrac{dy}{dx} = \dfrac{1-e^{-\frac{10}{3} \ln(...
gatecse
4.0k
points
gatecse
asked
Feb 17, 2018
Hydraulics
gate2018-ce-1
numerical-answers
water-resource-engineering
hydraulics
flow-measurement-in-channels
eulers-method
+
–
To see more, click for the
full list of questions
or
popular tags
.
GO Civil
Email or Username
Show
Hide
Password
I forgot my password
Remember
Log in
Register