In case of bids in Two-Envelop System, the correct option is

  1. Technical bid is opened first
  2. Financial bid is opened first
  3. Both (Technical and Financial) bids are opened simultaneously
  4. Either of the two (Technical and Financial) bids can be opened first
in Construction Materials and Management by (5.2k points)