The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below in arrows.

The critical duration for this construction project is

  1. $13$ days
  2. $14$ days
  3. $15$ days
  4. $16$ days