Login
Register
Dark Mode
Brightness
Ambient Glow – Questions list
Register
Profile
Edit Profile
Messages
My favorites
My Updates
Logout
Filter
No answer
No selected answer
No upvoted answer
Featured
Previous GATE
Questions without answers in Construction Materials and Management
0
0 votes
0
0 answers
GATE Civil 2025 Set 2 | Question: 13
In the context of construction materials, which of the following statements is/are CORRECT?If the characteristic strength is defined as that value below which not more th...
Shubham Sharma 2
427
points
asked
Mar 6, 2025
Construction Materials and Management
gatecivil-2025-set2
construction-materials-and-management
concrete-structures
steel-structures
+
–
0
0 votes
0
0 answers
GATE Civil 2025 Set 1 | Question: 23
If the weights retained on the $2.36 \: \mathrm{~mm}, 1.18 \: \mathrm{~mm}, 600 \: \mu \mathrm{~m}$, and $300 \: \mu \mathrm{~m}$ sieves are $30 \%, 35 \%, 15 \%$, and $2...
Shubham Sharma 2
427
points
asked
Mar 6, 2025
Construction Materials and Management
gatecivil-2025-set1
numerical-answers
construction-materials-and-management
+
–
0
0 votes
0
0 answers
GATE Civil 2025 Set 1 | Question: 32
In the context of construction project management, which of the following statements is/are true:A dummy activity will consume time and resourcesThe programme evaluat...
Shubham Sharma 2
427
points
asked
Mar 6, 2025
Construction Materials and Management
gatecivil-2025-set1
construction-materials-and-management
project-planning-and-network-analysis
+
–
0
0 votes
0
0 answers
GATE Civil 2024 Set 2 | Question: 7
Consider the statements $\text{P}$ and $\text{Q}$.$\text{P}$: In a Pure project organization, the project manager maintains complete authority and has maximum control...
Arjun
4.6k
points
asked
Feb 16, 2024
Construction Materials and Management
gatecivil-2024-set2
construction-materials-and-management
+
–
0
0 votes
0
0 answers
GATE Civil 2024 Set 2 | Question: 9
Consider the following data for a project of $300$ days duration.Budgeted Cost of Work Scheduled (BCWS) = Rs. $200$Budgeted Cost of Work Performed (BCWP) = Rs. $150$...
Arjun
4.6k
points
asked
Feb 16, 2024
Construction Materials and Management
gatecivil-2024-set2
construction-materials-and-management
numerical-answers
+
–
0
0 votes
0
0 answers
GATE Civil 2024 Set 2 | Question: 28
A critical activity in a project is estimated to take $15$ days to complete at a cost of Rs. $30,000$. The activity can be expedited to complete in $12$ days by spendi...
Arjun
4.6k
points
asked
Feb 16, 2024
Construction Materials and Management
gatecivil-2024-set2
construction-materials-and-management
numerical-ability
+
–
0
0 votes
0
0 answers
GATE Civil 2024 Set 2 | Question: 42
The table shows the activities and their durations and dependencies in a project.\begin{array}{|c|c|c|}\hline \text{Activity} & \text{Duration (Days)} & \text{Depends on}...
Arjun
4.6k
points
asked
Feb 16, 2024
Construction Materials and Management
gatecivil-2024-set2
numerical-answers
project-planning-and-network-analysis
+
–
0
0 votes
0
0 answers
GATE Civil 2024 Set 1 | Question: 41
The initial cost of an equipment is Rs. $1,00,000$. Its salvage value at the end of accounting life of $5$ years is Rs. $10,000$. The difference in depreciation (in Rs.) ...
admin
203
points
asked
Feb 16, 2024
Construction Materials and Management
gatecivil-2024-set1
numerical-answers
construction-materials-and-management
quantitative-aptitude
+
–
0
0 votes
0
0 answers
GATE Civil 2023 Set 1 | Question: 5
In cement concrete mix design, with the increase in water-cement ratio, which one of the following statements is TRUE? Compressive strength decreases but workability incr...
admin
203
points
asked
May 21, 2023
Construction Materials and Management
gatecivil-2023-set1
concrete-structures
construction-materials-and-management
+
–
0
0 votes
0
0 answers
GATE Civil 2022 Set 2 | Question: 5
Match all the possible combinations between Column X (Cement compounds) and Column Y (Cement properties):$$\begin{array} {|l|l|} \hline \textbf{Column X} & \qquad \textbf...
Arjun
4.6k
points
asked
Feb 15, 2022
Construction Materials and Management
gatecivil-2022-set2
construction-materials-and-management
concrete-structures
+
–
0
0 votes
0
0 answers
GATE Civil 2022 Set 2 | Question: 43
The activities of a project are given in the following table along with their durations and dependency.$$ \begin{array} {|c|c|c|} \hline \textbf{Activities}& \textbf{Dura...
Arjun
4.6k
points
asked
Feb 15, 2022
Construction Materials and Management
gatecivil-2022-set2
numerical-answers
construction-materials-and-management
+
–
0
0 votes
0
0 answers
GATE Civil 2022 Set 2 | Question: 54
It is given that an aggregate mix has $260 \; \text{grams}$ of coarse aggregates and $240 \; \text{grams}$ of fine aggregates. The specific gravities of the coarse and fi...
Arjun
4.6k
points
asked
Feb 15, 2022
Construction Materials and Management
gatecivil-2022-set2
numerical-answers
construction-materials-and-management
+
–
0
0 votes
0
0 answers
GATE Civil 2022 Set 1 | Question: 5
Which of the following equations is correct for the Pozzolanic reaction?$\text{Ca(OH)}_{2}$ + Reactive Superplasticiser + $H_{2}O \rightarrow \text{C-S-H}$$\text{Ca(OH)}_...
Arjun
4.6k
points
asked
Feb 15, 2022
Construction Materials and Management
gatecivil-2022-set1
construction-materials-and-management
concrete-structures
+
–
0
0 votes
0
0 answers
GATE Civil 2022 Set 1 | Question: 29
The project activities are given in the following table along with the duration and dependency.$$\begin{array}{|c|c|} \hline \textbf{Activities} & \textbf{Duration (days...
Arjun
4.6k
points
asked
Feb 15, 2022
Construction Materials and Management
gatecivil-2022-set1
construction-materials-and-management
+
–
0
0 votes
0
0 answers
GATE Civil 2021 Set 2 | Question: 8
Seasoning of timber for use in construction is done essentially toincrease strength and durabilitysmoothen timber surfacesremove knots from timber logscut timber in right...
go_editor
999
points
asked
Mar 1, 2021
Construction Materials and Management
gatecivil-2021-set2
construction-materials
material-behaviour
timber
+
–
0
0 votes
0
0 answers
GATE Civil 2021 Set 2 | Question: 9
In case of bids in Two-Envelop System, the correct option isTechnical bid is opened firstFinancial bid is opened firstBoth (Technical and Financial) bids are opened simul...
go_editor
999
points
asked
Mar 1, 2021
Construction Materials and Management
gatecivil-2021-set2
construction-materials-and-management
bidding
+
–
0
0 votes
0
0 answers
GATE Civil 2021 Set 2 | Question: 42
The activity details for a small project are given in the Table.$$\begin{array}{|cl|cI|cI|}\hline&\textbf{Activity} & \textbf{Duration (days)} & \textbf{Depends on} \\ \h...
go_editor
999
points
asked
Mar 1, 2021
Construction Materials and Management
gatecivil-2021-set2
numerical-answers
construction-materials-and-management
project-planning-and-network-analysis
+
–
0
0 votes
0
0 answers
GATE Civil 2021 Set 2 | Question: 43
An equipment has been purchased at an initial cost of $₹ 160000$ and has an estimated salvage value of $₹ 10000$. The equipment has an estimated life of $5$ years. The di...
go_editor
999
points
asked
Mar 1, 2021
Construction Materials and Management
gatecivil-2021-set2
numerical-answers
cost-estimation
+
–
0
0 votes
0
0 answers
GATE Civil 2021 Set 1 | Question: 5
Gypsum is typically added in cement toprevent quick settingenhance hardeningincrease workabilitydecrease heat of hydration
Arjun
4.6k
points
asked
Feb 19, 2021
Construction Materials and Management
gatecivil-2021-set1
material-behaviour
+
–
0
0 votes
0
0 answers
GATE Civil 2021 Set 1 | Question: 6
The direct and indirect costs estimated by a contractor for bidding a project is $₹160000$ and $₹20000$ respectively. If the mark up applied is $10\%$ of the bid price, t...
Arjun
4.6k
points
asked
Feb 19, 2021
Construction Materials and Management
gatecivil-2021-set1
construction-contracts
cost-estimation
+
–
0
0 votes
0
0 answers
GATE Civil 2021 Set 1 | Question: 30
Contractor $\text{X}$ is developing his bidding strategy against Contractor $\text{Y}$. The ratio of $\text{Y’s}$ bid price to $\text{X’s}$ cost for the $30$ previous bid...
Arjun
4.6k
points
asked
Feb 19, 2021
Construction Materials and Management
gatecivil-2021-set1
construction-materials-and-management
bidding
+
–
0
0 votes
0
0 answers
GATE2020-CE-1-6
A reinforcing steel bar, partially embedded in concrete, is subjected to a tensile force $P$. The figure that appropriately represents the distribution of the magnitude o...
go_editor
999
points
asked
Feb 27, 2020
Construction Materials and Management
gate2020-ce-1
structural-steel-composition
reinforced-steel
+
–
0
0 votes
0
0 answers
GATE2020-CE-1-8
During the process of hydration of cement, due to increase in Dicalcium Silicate $(C_2S)$ content in cement clinker, the heat of hydrationincreasesdecreasesinitially decr...
go_editor
999
points
asked
Feb 27, 2020
Construction Materials and Management
gate2020-ce-1
concrete-mix-design
cement-properties
clinker
+
–
0
0 votes
0
0 answers
GATE2020 CE-2-8
As per $IS\:456:2000$, the $pH$ value of water for concrete mix shall NOT be less than$4.5$$5.0$$5.5$$6.0$
go_editor
999
points
asked
Feb 13, 2020
Construction Materials and Management
gate2020-ce-2
construction-materials-and-management
concrete-mix-design
+
–
0
0 votes
0
0 answers
GATE2017 CE-2-15
Let the characteristic strength be defined as that value, below which not more than $50 \%$ of the results are expected to fall. Assuming a standard deviation of $4$ MPa,...
gatecse
615
points
asked
Aug 7, 2019
Construction Materials and Management
gate2017-ce-2
construction-materials-and-management
structural-engineering
concrete-mix-design
+
–
0
0 votes
0
0 answers
GATE2017 CE-2-18
For a construction project, the mean and standard deviation of the completion time are $200$ days and $6.1$ days, respectively. Assume normal distribution and use the val...
gatecse
615
points
asked
Aug 7, 2019
Construction Materials and Management
gate2017-ce-2
numerical-answers
construction-materials-and-management
structural-engineering
construction-project
+
–
0
0 votes
0
0 answers
GATE2017 CE-2-30
Group I gives a list of test methods and test apparatus for evaluating some of the properties of Ordinary Portland Cement (OPC) and concrete. Group II gives the list of t...
gatecse
615
points
asked
Aug 7, 2019
Construction Materials and Management
gate2017-ce-2
structural-engineering
construction-materials-and-management
concrete-constituents--mix-design
+
–
0
0 votes
0
0 answers
GATE2017 CE-2-33
Consider the following statements:Walls of one brick thick are measured in square metersWalls of one brick thick are measured in cubic metersNo deduction in the brickwork...
gatecse
615
points
asked
Aug 7, 2019
Construction Materials and Management
gate2017-ce-2
construction-materials-and-management
structural-engineering
bricks
+
–
0
0 votes
0
0 answers
GATE2019 CE-1: 37
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of ...
Arjun
4.6k
points
asked
Feb 14, 2019
Construction Materials and Management
gate2019-ce-1
numerical-answers
construction-materials-and-management
structural-engineering
construction-project
cost-estimation
+
–
0
0 votes
0
0 answers
GATE2019 CE-2: 7
If the fineness modulus of a sample of fine aggregates is $4.3$, the mean size of the particles in the sample is between$150 \: \mu m$ and $300 \: \mu m$$300 \: \mu m$ an...
Arjun
4.6k
points
asked
Feb 12, 2019
Construction Materials and Management
gate2019-ce-2
structural-engineering
construction-materials-and-management
material-behaviour
+
–
0
0 votes
0
0 answers
GATE2019 CE-2: 21
The characteristic compressive strength of concrete required in a project is $25 \: MPa$ and the standard deviation in the observed compressive strength expected at site ...
Arjun
4.6k
points
asked
Feb 12, 2019
Construction Materials and Management
gate2019-ce-2
numerical-answers
construction-materials-and-management
structural-engineering
concrete-mix-design
+
–
0
0 votes
0
0 answers
GATE2016-2-9
As per Indian standards for bricks, minimum acceptable compressive strength of any class of burnt clay bricks in dry state is$10.0 \text{ MPa}$$7.5 \text{ MPa}$$5.0 \text...
Milicevic3306
1.1k
points
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-2
construction-materials-and-management
structural-engineering
bricks
+
–
0
0 votes
0
0 answers
GATE2016-2-10
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network di...
Milicevic3306
1.1k
points
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-2
construction-materials-and-management
structural-engineering
project-planning-and-network-analysis
cost-estimation
+
–
0
0 votes
0
0 answers
GATE2016-2-39
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below in ...
Milicevic3306
1.1k
points
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-2
construction-materials-and-management
structural-engineering
project-planning-and-network-analysis
+
–
0
0 votes
0
0 answers
GATE2016-1-9
Bull’s trench kiln is used in the manufacturing oflimecementbricksnone of these
Milicevic3306
1.1k
points
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-1
bulls-trench-kiln
structural-engineering
construction-materials-and-management
construction-materials
+
–
0
0 votes
0
0 answers
GATE2016-1-10
The compound which is largely responsible for initial setting and early strength gain of Ordinary Portland Cement is$C_3A$$C_3S$$C_2S$$C_4AF$
Milicevic3306
1.1k
points
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-1
structural-engineering
construction-materials-and-management
concrete-mix-design
+
–
0
0 votes
0
0 answers
GATE2016-1-39
The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O – M – P.The expect...
Milicevic3306
1.1k
points
asked
Mar 27, 2018
Construction Materials and Management
gate2016-ce-1
numerical-answers
structural-engineering
construction-materials-and-management
project-planning-and-network-analysis
+
–
0
0 votes
0
0 answers
GATE2017 CE-1: 45
The activity details of a project are given below:$$\begin{array}{|c|c|c|} \hline \text{Activity} & \text{Depends on} & \text{Duration (in days)} \\ \hline P & \dots & 6 ...
Milicevic3306
1.1k
points
asked
Mar 26, 2018
Construction Materials and Management
gate2017-ce-1
numerical-answers
construction-materials-and-management
structural-engineering
project-planning-and-network-analysis
cost-estimation
+
–
0
0 votes
0
0 answers
GATE2015-2-53
In Marshall method of mix design, the coarse aggregate, fine aggregate, fines and bitumen having respective values of specific gravity $2.60, 2.70, 2.65$ and $1.01$, are ...
Milicevic3306
1.1k
points
asked
Mar 26, 2018
Construction Materials and Management
gate2015-ce-2
construction-materials-and-management
mix-design
marshall-method
structural-engineering
+
–
0
0 votes
0
0 answers
GATE2015-1-4
Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete.As the slump increases...
Milicevic3306
1.1k
points
asked
Mar 26, 2018
Construction Materials and Management
gate2015-ce-1
structural-engineering
construction-materials-and-management
workability-of-concrete
material-properties-and-behaviour
+
–
To see more, click for the
full list of questions
or
popular tags
.